Oasis Marina – May 2009 update The month of May saw the contractors continuing with the concrete work for the villas apartment blocks. Pictures 1 and 2 shows the reinforced rods being laid for the roof of two villa blocks. Once the reinforced metal is in place and before the concrete, all the electrical cables must be laid and in place. Picture 3 shows the orange cables that will eventually be used for the electrical wires for the apartment block. Picture 4 shows the concrete being laid and Picture 5 shows an apartment block with the concrete work complete. The next stage will be the brickwork for the block. We intend to do the brick work in several blocks at the same time, so the it is important for us to continue with the concrete work which is the most time consuming. Picture 6 shows concrete being laid in villa block G & H. |