Oasis Marina – March 2010 update March saw the continuing progress of Oasis Marina. The month started with the plastering contractors working hard on completing the villa apartments that still has outstanding plastering work (Pictures 1 & 2). By late March the vast majority of plaster rendering had been completed and the painting contractors moved to paint the first few coats on the remaining villa blocks (pictures 3-6). Although the villa apartments, being the front line apartment, have shown great advancement, work is still continuing with the apartment blocks (pictures 7-9). The level of work has meant that there are almost frequent daily deliveries of building materials to the Oasis Marina site (picture 10). The concrete works contractor has workmen who continually prepare the metal rods for the concrete works (picture 11). The final picture (12) was taken from the roof from a villa block and Giftun Island can be seen in the distance. |